A mechanic's lien is a legal document used by contractors, subcontractors, and suppliers to secure payment for work completed on a construction project. Filing a mechanic's lien essentially states that:
- You're owed money for services provided
- You're expecting payment by a specific date
- You'll proceed with litigation if you don't receive payment by that date
While a lien is in place, it restricts the owner from selling, refinancing, or transferring the property without paying you. That pressure makes liens one of the most powerful payment tools available—especially for subcontractors and suppliers.
Mechanic's lien laws vary significantly by state, with different rules governing who can file a lien, what notices are required, and timelines for filing and enforcement. This guide covers the essentials of California's mechanic's lien laws to help you protect your right to payment.
Must send a 20-Day Preliminary Notice to the lender (if any).
Late notice is allowed, but only protects the prior 20 days of work.
Must send a 20-Day Preliminary Notice to owner, GC, and lender (if any).
Late notice is allowed, but only protects the prior 20 days of work.
Not required
Not required
Not required
Not required
Within 90 days after completion, unless a Notice of Completion is recorded, then 60 days
Within 90 days after completion, unless a Notice of Completion is recorded, then 30 days
Within 90 days after completion, unless a Notice of Completion is recorded, then 30 days
Within 90 days after recording the lien
Same as GC
Same as GC
Unpaid contract balance
Reasonable value of unpaid labor, materials, or equipment furnished, capped at what owner owes GC
Unpaid value of furnished labor
California mechanic's liens are governed by California Civil Code §§ 8000–9566, and they only apply to private works of improvement. (You can't lien public projects in California. Instead, payment is enforced through stop payment notices and payment bond claims.)
California gives lien rights to a broad group of parties, but it is also one of the most notice- and deadline-driven states. Most subcontractors and suppliers must serve a 20-day preliminary notice early in the project, and lien filing deadlines can be shortened if the owner records a Notice of Completion or Notice of Cessation.
Missing a notice, miscalculating completion, or overlooking a recorded owner notice can invalidate an otherwise valid lien—so timing and documentation matter.
California allows the following private-project claimants to record a mechanic’s lien:
- General (original) contractors
- Subcontractors (all tiers)
- Material suppliers (except suppliers to suppliers)
- Equipment lessors
- Laborers
- Fringe-benefit trust funds
Important nuances:
- Suppliers to suppliers do not have lien rights.
- Haulers/transporters only have lien rights if they own the materials, contribute to the improvement, or are hired by the owner’s agent.
- Proper contractor licensing is critical—unlicensed work can bar lien rights and trigger repayment obligations.
Under Civ. Code §§ 8046 and 8050, a mechanic’s lien may be claimed for labor, services, equipment, or materials that contribute to a “work of improvement” (a.k.a. adds value to a property).
Here are examples of what’s considered lienable and what isn’t.
Lienable Work in California
- Construction, alteration, or repair of a structure
- Permanent improvements (framing, drywall, mechanical, electrical, plumbing, roofing, concrete, paving)
- Site improvements such as grading, excavation, utilities, trenching, and demolition
- Materials, fixtures, and equipment incorporated into the improvement
- Equipment rental used in the work of improvement
- Labor, supervision, and on-site project management tied to the improvement
- Delivery of materials when the supplier is furnishing to a contractor or subcontractor (not to another supplier)
- Off-site fabrication custom-made for the project when it becomes part of the improvement
Non-Lienable Work in California
- Work on public property
- Tools, equipment, or materials not incorporated into the improvement
- Purely administrative, clerical, or consulting services not directly tied to physical improvement
- GC overhead not associated with labor or materials for the job
- Penalties, liquidated damages, interest, or unrelated debts
- Maintenance work or temporary fixes that do not permanently improve the property
- Work performed under a tenant contract when the owner records and posts a valid Notice of Nonresponsibility within 10 days of learning of the project
Before filing a lien, ensure that you’ve met any preliminary notice requirements that apply to your role (see table above).
Deadline to File
In California, your filing deadline depends on whether the owner recorded a Notice of Completion or Notice of Cessation.
If Notice of Completion/Cessation is Filed
If the project owner records either of these, the time frame to record a mechanic’s lien shrinks:
- Subcontractors and suppliers have 30 days
- General contractors have 60 days
If the owner records the notice but fails to send it to claimants who served a preliminary notice, the shortened deadline usually does not apply and the full 90-day period. Still, it’s smart to monitor recording activity so you know immediately if a deadline changes.
If No Notice is Filed
All claimants must file a lien claim within 90 days after “completion” of the work, which occurs when:
- The project is finished,
- The owner uses/occupies the property and labor stops,
- Work stops for 60 days, or
- A Notice of Cessation is recorded after 30 days of stoppage.
Filing early (before completion) can invalidate the lien. (See full definition of completion under Civ. Code § 8180.)
Filing Requirements
- Where to file: File the lien claim at the county recorder in the county where the property is located.
- Form requirements: California doesn’t mandate a statutory lien claim form, but it must include:
- Claimant’s name and address
- Owner or reputed owner
- Name of the party who contracted for the work
- A general statement of the labor, materials, or equipment furnished
- The amount due (reasonable value or contract price, whichever is less)
- Property description sufficient for identification (legal description preferred)
- Construction lender (if known)
- A mandatory block of text printed on the lien in 10-point boldface that says “Notice of Mechanic’s Lien” (Civ. Code § 8416)
- An attached proof of service affidavit showing the lien was mailed to owner
- Verification: Must be signed under penalty of perjury; notarization not required.
- Filing fee: Varies by county (typically ~$20-$40 for the first page plus per-page charges).
Service Requirements
A copy of the recorded mechanic’s lien must be served on the property owner (or reputed owner) within a reasonable time after recording. Service is typically completed by certified mail, registered mail, express mail, or personal delivery, and proof of service must be retained.
Recording a lien preserves your rights—but enforcement is how you get paid. Here’s what you must do to ensure you enforce your lien in California.
Enforcement Requirements
- Enforcement deadline: A foreclosure lawsuit must be filed within 90 days after recording the lien.
- Lis pendens: A notice of pendency action (lis pendens) must be recorded within 20 days after filing the foreclosure lawsuit. Most file it with the foreclosure lawsuit to save a step.
- Filing location: File both documents in the Superior Court in the county where the property is located.
- Lien priority: In California, mechanic’s liens generally outrank mortgages or other liens recorded after construction begins, and multiple lien claimants typically share priority and are paid proportionally.
Lien Release Requirements
Once a lien is paid, the claimant must promptly record a Release of Mechanic's Lien with the county recorder. Failure to release a lien can result in damages, penalties, and attorney’s fees (Cal. Civ. Code § 8480).
- Unified workflow: Manage lien rights within your billing and collections workflow to keep payment context in one place.
- Automated compliance: Automatically track critical deadlines and milestones based on each state's lien laws.
- Meaningful visibility: View the lien protection status for each project to identify and mitigate risk.
- Document creation: Generate state-specific lien notices instantly using existing project data
- Integrated delivery: Send notices via certified mail directly from Siteline to streamline delivery.
No. If your work requires a contractor’s license and you weren’t licensed at the start of work, you cannot lien—and you may even have to return payments already received.
Yes. California protects subcontractors, suppliers, equipment lessors, laborers, and others who contribute to the improvement—as long as the preliminary notice was properly served.
Yes, but for lien filing only. If the owner records either a Notice of Completion or Notice of Cessation, lien filing deadlines shorten to:
- 30 days for subs and suppliers
- 60 days for GCs
If the owner fails to notify you—and you served a preliminary notice—the shortened deadline usually doesn’t apply (Cal. Civ. Code § 8182; § 8188).
No. California does not require a Notice of Intent to lien before recording a mechanic’s lien.
If you don’t contract directly with the owner, then yes, you must submit a 20-day preliminary notice to preserve your lien rights.
Yes. California is one of the few states that mandates statutory waiver forms. See all California lien waiver requirements here.
You can lien for the reasonable value of labor, materials, or equipment furnished—or the contract price, whichever is less. This can include labor, materials, equipment rental, approved change orders, custom fabrication, and site improvement work.
For subcontractors and suppliers, actual recovery may be limited to the amount the owner still owes the GC at the time the lien is enforced.
You generally cannot include interest, attorney’s fees, or unrelated damages in the lien amount unless later awarded by the court.
Not always, but it helps. California allows liens based on oral or written agreements, but you must be able to prove that the work was performed and the amount is owed. GCs, however, must finish their contract before recording a lien.
Disclaimer: This guide is for informational purposes only and does not constitute legal advice. Always consult with a qualified construction attorney in your state regarding specific legal matters before taking any action that could affect your lien rights.